8/6/2015 - Downtown Streetscape Well Underway!



Phase IIIa of the Downtown Streetscape began on Monday, August 3, 2015.
Plans for S. Ohio Avenue from 7th Street to Broadway
Avenue include a new
street, sidewalks, water lines, street lights and an arch north of the intersection
of Ohio Avenue and Broadway. KAT Excavation was awarded the contract for
$750,648.62 and the Notice to Proceed was given on August 3, 2015. Completion
date is scheduled for October 31, 2015
.